Maintenance Schedule Optimization for Turnaround Hot Gas Path Inspection of Gas Turbine in North Duri Cogeneration Plant Using Impact Method

Hariyanto, BenyRomy, Romy
Journal of Ocean, Mechanical and Aerospace -science and engineering- (Sinta 3)Vol. 0 No. 030 Maret 2020
DOI10.36842/jomase.v64i1.159

Abstrak

North Duri Cogeneration Plant (NDC) is once of Chevron asset in IndoAsia Business Unit. The NDC location is in Duri, Province of Riau, Indonesia. The NDC has 3 units gas turbine and each unit has been combined with Heat Recovery Steam Generator (HRSG). An unit gas turbine NDC is produce electricity of 100 MW, and 1 unit of HRSG NDC that is produce steam of 360,000 BCWEPD (Barrel Cool Water Equivalent per Day). Hot gas path inspection (HGPI) is maintenance activities gas turbine, which routine scheduled in NDC every 3 years per unit. Maintenance schedule for turnaround HGPI gas turbine at NDC should be optimizing. By optimized of HGPI maintenance schedule can be maximized work plan, which is comply of 4 Key Performance Indicators there are Safety, Quality, Schedule and Cost through Initiative for Managing PACesetter Turnarounds (IMPACT). The result of optimal electricity production was increased by 13,174 MWh and the steam generated from units in NDC of mass total steam of 126,661 Mlbm and 371,827 BSPD.

Cari jurnal yang tepat untuk naskah Anda

MatchMind AI mencocokkan abstrak naskah Anda dengan ribuan jurnal terakreditasi dan menampilkan rekomendasi terbaik beserta alasannya.

Coba MatchMind

Lihat profil lengkap jurnal ini

Waktu review, biaya APC, statistik sitasi, indeksasi Scopus, dan banyak lagi.

Buka Journal of Ocean, Mechanical and Aerospace -science and engineering-

Artikel ini juga tersedia di situs resmi jurnal.

Maintenance Schedule Optimization for Turnaround Hot Gas Path Inspection of Gas Turbine in North Duri Cogeneration Plant Using Impact Method | Journal of Ocean, Mechanical and Aerospace -science and engineering- | Publiora